The capital work currently on the books in Lake Wales — what it is, where it is, what it costs, and which fund pays for it. Every project links back to its fund in the civic handbook.

FY 2026–2027 budget

Funded in the proposed budget

These three projects are line items in the proposed FY 2026–2027 budget. Final adoption should be confirmed against the adopted ordinance before being cited as final.

  • Funded in the proposed FY 2026–2027 budget

    Street resurfacing & pavement preservation

    Roughly 5 to 6 miles of city streets resurfaced under the pavement preservation plan, plus restriping, sidewalk repair, and a new curb and concrete rehabilitation program.

    Citywide · $1,000,000

  • Funded in the proposed FY 2026–2027 budget

    Memorial Gardens Cemetery expansion, phase 2

    Completion of the second phase: 1,190 adult lots, 48 children's lots, and 272 cremation spaces, with office, equipment barn, signage, and staffing improvements.

    Memorial Gardens Cemetery

  • Funded in the proposed FY 2026–2027 budget

    City Hall emergency generator

    A permanent emergency generator for City Hall. Installation is anticipated in FY 2027 because of a 25 to 29 week equipment lead time.

    City Hall, 201 W Central Ave

Ongoing capital work

CRA and citywide projects

Longer-running projects carried in the CRA annual report and the city's capital lines. Stage language is deliberately coarse — we report what the records say and do not invent completion dates.

Follow the money

Every project above is paid out of a specific fund. The civic handbook explains each fund, where its money comes from, and the hearings where it was adopted — or track the whole cycle on the budget timeline.